Situation before the contract and client requirements
Client used old meters from 1950 with no communication system in place.
In order to check energy consumption, manual control of 114 electricity meters had to be performed.
The client wanted 114 new electricity meters.
The client requested automatic acquisition of data on the consumption of electricity, power, current and voltage.
Resalta solution
Installation of 114 new meters with Modbus communication systems in 4 electricity substations.
The new meters communicate data to the server via fiber optics.