Topolšica Hotel & Spa - Slovenia

Project statistics

Reduction of heating costs by

54

%

Installation of cooling in hotel rooms

Installation of a parallel heating system

Situation before the contract and client requirements


The Topolšica hotel and spa operates year-long and has a constant demand for heat.

Its heating system was wasteful, obsolete and unreliable, with numerous fall-outs. In addition the hotel was subject to the high price of district heating, thus incurring considerable costs for a system that could not meet all its needs.

Resalta solution

Resalta installed a 1.1 MW heat pump (water/water) as the main heat source. 

A new 100kW chiller (water/water) was installed to provide cooling for 61 rooms with fan-coils, with the possibility of connecting the remaining 61 rooms to the same system.

The heat pump has increased the demand for underground water and in order to reduce the cost of additional drawing rights, an existing pool waste water recovery system was installed. The existing boiler room was reconstructed to retain the existing system as a back up for periods of peak demand.

Want to see more?

Download our brochure.

Terms and conditions.

By subscribing to our newsletter you agree to receive e-mail communications from Resalta d.o.o. The aim of our newsletter is to keep visitors to the website, partners, clients and the general public informed of the work Resalta does, its new projects, developments, upcoming events as well as news concerning energy efficiency and renewables. The frequency of the newsletter issues will be at most monthly, with possible exceptions for unscheduled yet important news. We reserve the sole right to either modify or discontinue the newsletter, at any time and without notice to you. We take your privacy seriously and will never communicate or sell your information to third parties. You can unsubscribe from the newsletter at any time.