Medvode Neighbourhood – Slovenia

Project statistics

Annual savings

20,000

Combined heat and power

Situation before the contract and client requirements

A neighbourhood in the town of Medvode was using a natural gas boiler for heating several blocks of buildings. 

The required heat was 810 MWh annually and the heating costs were too high for the neighbourhood.

Resalta solution

Resalta analyzed the actual heating energy demand and installed an appropriately-sized cogeneration of heat and power (CHP) plant on natural gas. 

Resalta installed a CHP unit with a 50 kW electricity capacity and 80 kW of thermal power capacity. 

Resalta is maintaining the plant and monitors the system through GGE‘s central control system (web access) in real time.

Want to see more?

Download our brochure.

Terms and conditions.

By subscribing to our newsletter you agree to receive e-mail communications from Resalta d.o.o. The aim of our newsletter is to keep visitors to the website, partners, clients and the general public informed of the work Resalta does, its new projects, developments, upcoming events as well as news concerning energy efficiency and renewables. The frequency of the newsletter issues will be at most monthly, with possible exceptions for unscheduled yet important news. We reserve the sole right to either modify or discontinue the newsletter, at any time and without notice to you. We take your privacy seriously and will never communicate or sell your information to third parties. You can unsubscribe from the newsletter at any time.