Situation before the contract and client requirements
The Terme Ptuj are located in the Ptuj Spa complex near the city of Maribor.
The old lighting system was inefficient, some of the luminaires were broken.
The total installed electric power before the reconstruction was 17.35 kW.
The annual electricity consumption was 69,396.8 kWh.
Resalta solution
Installation of 142 energy efficient LED luminaires.
The total installed electric power after reconstruction is 5.79 kW.