Project statistics

Reduction of electricity consumption

67

%

Situation before the contract and client requirements

The Terme Ptuj are located in the Ptuj Spa complex near the city of Maribor. 

The old lighting system was inefficient, some of the luminaires were broken. 

The total installed electric power before the reconstruction was 17.35 kW. 

The annual electricity consumption was 69,396.8 kWh. 

Resalta solution

Installation of 142 energy efficient LED luminaires. 

The total installed electric power after reconstruction is 5.79 kW. 

Want to see more?

Download our brochure.

Terms and conditions.

By subscribing to our newsletter you agree to receive e-mail communications from Resalta d.o.o. The aim of our newsletter is to keep visitors to the website, partners, clients and the general public informed of the work Resalta does, its new projects, developments, upcoming events as well as news concerning energy efficiency and renewables. The frequency of the newsletter issues will be at most monthly, with possible exceptions for unscheduled yet important news. We reserve the sole right to either modify or discontinue the newsletter, at any time and without notice to you. We take your privacy seriously and will never communicate or sell your information to third parties. You can unsubscribe from the newsletter at any time.